he Perform Integrated Change Control pro

资格题库2022-08-02  18

问题 he Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ().A.Change control boardB.Project management officeC.Project managerD.Configuration management officer

选项

答案 C

解析 项目整体变更控制流程贯穿于项目开始到项目完成的各阶段,并且最终是()的职责。A.变更控制委员会B.项目管理办公室C.项目经理D.配置管理员
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301720.html

最新回复(0)