The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ).A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
整体变更控制过程的实施从项目开始到结束一直进行。这是(项目经理PM)的最终责任。
A.变更控制委员会CCB
B.项目管理办公室PMO
C.项目经理PM
D.配置管理专员CMO
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302919.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
ThePerformIntegratedChangeControlpr
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
WhoKilledtheSeaLions?A)Sittingintheturbulent(汹涌的
[originaltext]M:Canwearingsunglassesmakeyoumorevulnerabletosunburn?A
目前,二段式种植体:A.种植周期较短 B.成功率低 C.成功率高 D.分为
智能终端不设置防跳功能,防跳功能由断路器本体实现。
以下是近代以来西方侵略者强迫清政府签订的不平等条约中的一个条款,请根据下述文字判
职业人格类型包括( )、艺术型。A.常规型 B.现实型 C.研究型 D.
下列属于货币型理财产品特点的有()。A.投资期限短 B.本金、收益安全性高
短期总供给曲线是一条曲右上方倾斜的曲线,这表明()。A:价格水平越高,投资的
下列哪一行为不成立使用假币罪(不考虑数额)? A.用假币缴纳罚款
根据《小型水电站建设工程验收规程》SL168-2012,水电站合同工程完工验收后
最新回复
(
0
)