The Perform Integrated Change Control pr
The Perform Integrated Change Control pr
题库
2022-08-02
45
问题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ).A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
整体变更控制过程的实施从项目开始到结束一直进行。这是(项目经理PM)的最终责任。
A.变更控制委员会CCB
B.项目管理办公室PMO
C.项目经理PM
D.配置管理专员CMO
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302919.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
ThePerformIntegratedChangeControlpr
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
Researchershavedeterminedthatwomenusebothsidesoftheirbrainforlis
Theexplosionofahydrogenbombistheresultofuncontrollednuclearfusion.I
PassageTwo(1)WhenWinstonChentoldhisfriendsthathehadquithis
Whydoesthestudentsaythatit’scomplicatedandembarrassing?[br][original
样本均值是总体均值的一个一致估计量。()
以下关于金融期权的说法正确的是() Ⅰ.金融期权是指其持有者能在规定的
盈余公积转增资本时,转增后留存的盈余公积的数额不得少于注册资本的()。A、20%
各种运输方式内外部的各个方面的构成和联系,就是( )。 A.运输系统
某市计划进行一次大规模的口腔健康教育,在大量的调查研究基础上制订了口腔健康教育目
水池满水试验时,应按要求向池内注水,下列各项要求正确的是()。A、向池内注水宜
最新回复
(
0
)