问题 The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the (  ).A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer

选项 A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer

答案 C

解析 整体变更控制过程的实施从项目开始到结束一直进行。这是(项目经理PM)的最终责任。
A.变更控制委员会CCB
B.项目管理办公室PMO
C.项目经理PM
D.配置管理专员CMO