The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ).A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
整体变更控制过程的实施从项目开始到结束一直进行。这是(项目经理PM)的最终责任。
A.变更控制委员会CCB
B.项目管理办公室PMO
C.项目经理PM
D.配置管理专员CMO
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302919.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
ThePerformIntegratedChangeControlpr
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
TheworkersofspaceshuttleDiscoverygotintothebackoftheshuttletolook
Howcouldfaithbegetsuchevil?AfterhundredsofmembersofaUgandancult
[originaltext]Miceingeneralarenotwell-liked,butamousenamedMickeyh
Allbutthetiniestofroadshavetohav
嗜铬细胞瘤的临床及超声表现,正确的是A.瘤体直径多在1.0~2.0cm,呈不规则
在PowerPoint中,能同时观看到多张幻灯片设计效果的“视图”的是()。A
为解决北方冬季传统燃煤方式对大气环境的污染,2017年2月17日,国家有关部委及
除另有规定外,应密封,置阴凉处贮存的制剂是A.散剂 B.注射剂 C.栓剂
预防龋病的关键环节是A:控制菌斑 B:控制糖的摄入 C:氟化物的应用 D:
先张法预应力筋的张拉过程中,张拉操作时,应对断丝情况进行检查,其要求()。A.
最新回复
(
0
)