问题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ).A.Chang control boardB.Project management officeC.Project managerD.Configuration management officer
选项
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
答案
C
解析
整体变更控制过程的实施从项目开始到结束一直进行。这是(项目经理PM)的最终责任。
A.变更控制委员会CCB
B.项目管理办公室PMO
C.项目经理PM
D.配置管理专员CMO
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302919.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Workperformanceinformationiscirculat
( )seektoperformrootcauseinvestiga
ThePerformIntegratedChangeControlpr
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
Youhavejusttakencontrolofaproject
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Yourhavejusttakencontrolofaprojec
随机试题
WhenDidAidsBegin?Theyea
Thecommittee__________aconclusionon
疮疡初起兼有表证应首选()。A.麻黄B.桂枝C.香薷D.荆芥E.防风
A.益母草浸膏B.颅通定C.丹参注射液D.莪术油注射液E.银杏叶提取物临床应用偶
如图是一物体某两个角度的视图,则该物体最可能是: A.如上图所示 B.如上图
编制某居住小区的修建性详细规划,其容积率控制指标为3.5,为妥善处理其较大的容积
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
(2020年真题)企业签订加工承揽合同支付的印花税,应计入加工承揽项目成本中。(
管道工程安装 建筑给水系统设有水箱时,水泵的扬程设置应()。 A.满足最不
以下为水痘皮疹特点,但除A.皮疹呈向心性分布 B.皮疹最初形态为斑丘疹 C.
最新回复
(
0
)