You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.A、Resource assignment matrix B、Change control planC、Project charter D、Client organization chart
选项
A、Resource assignment matrix
B、Change control plan
C、Project charter
D、Client organization chart
答案
B
解析
在项目执行的过程中你刚刚获得项目的控制权利,并且需要了解谁具有范围修正的权限,什么文件提供了该信息。
A.资源分配矩阵
B.变更控制计划
C.项目章程
D.客户的组织结构图
转载请注明原文地址:https://www.tihaiku.com/congyezige/2297223.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
Establishingaproject( )involveslis
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
随机试题
WhenDidAidsBegin?Theyea
Thecommittee__________aconclusionon
疮疡初起兼有表证应首选()。A.麻黄B.桂枝C.香薷D.荆芥E.防风
A.益母草浸膏B.颅通定C.丹参注射液D.莪术油注射液E.银杏叶提取物临床应用偶
如图是一物体某两个角度的视图,则该物体最可能是: A.如上图所示 B.如上图
编制某居住小区的修建性详细规划,其容积率控制指标为3.5,为妥善处理其较大的容积
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
(2020年真题)企业签订加工承揽合同支付的印花税,应计入加工承揽项目成本中。(
管道工程安装 建筑给水系统设有水箱时,水泵的扬程设置应()。 A.满足最不
以下为水痘皮疹特点,但除A.皮疹呈向心性分布 B.皮疹最初形态为斑丘疹 C.
最新回复
(
0
)