Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule
选项
A.cost management plan
B.risk management plan
C.scope management plan
D.management schedule
答案
D
解析
建立一个项目(进度管理计划)包含列出里程碑、活动和可交付的计划起止日期,其中要考虑到员工的安排的因素。
A.成本管理计划
B.风险管理计划
C.范围管理计划
D.进度管理计划
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302550.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
Surfacewaterwassampledbi-monthlyoveraone-yearperiodatsevensites_____
The(i)______ofgamblers’unsuccessfuldecisionstrategiesisone(ii)______of
请回答隧道环境检测设备技术要求的相关提问。(1)隧道环境设备主要质量评定标准是(
患者,14岁。身高132cm,体重24kg,形体均匀矮小,头颅无畸形,智力发育一
内痔的临床表现?
患者脘腹痞塞不舒,胸隔满闷,头晕目眩,身重困倦,呕恶纳呆,口淡不渴,舌苔白厚腻,
生态学是()。 A.研究植物、动物与环境之间相互关系的科学 B.研究植物、
急性肾衰竭多尿期常见的死亡原因为 A.髙钾血症B.低钾血症C.低钠血症D
狼孩的故事说明了教育必须顺应儿童发展的()。 A.顺序性 B.不平衡性 C
最新回复
(
0
)