In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ( )are not output of activity definition.A.Activity listB.Work Breakdown StructuresC.Activity AttributesD.Milestone Lists
选项
A.Activity list
B.Work Breakdown Structures
C.Activity Attributes
D.Milestone Lists
答案
B
解析
项目时间管理中, 定义活动是识别和记录为完成项目可交付成果而需采取的具体行动的过程,以下()不是定义活动的输出。A.活动清单B.工作分解结构C.活动属性D.里程碑清单定义活动包括:活动清单、活动属性、里程碑清单。故B选项不是 进度管理过程
转载请注明原文地址:https://www.tihaiku.com/congyezige/2303628.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Qualitymanagementensuresthatanorgan
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
( )managementincludesnegotiatingthe
Projectmanagerbelievesthatmodifying
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
随机试题
Hispoliticalfuture______ontheoutcomeofthiselection.A、hindersB、hingesC
工作在UDP协议之上的协议是()。A.HTTP B.Telnet
经抗酸染色找到结核杆菌报告为"++++"的细菌数量为A.每100个油镜视野1~9
(2018年)某商业银行(增值税一般纳税人)2018年第一季度提供贷款服务取得含
一般初孕妇开始自觉胎动的时间是在妊娠的第A.10~16周B.12~36周C.37
下列关于城市社会空间结构经典模式的表述,错误的是( )。A.同心圆模型最外层为
中国革命无产阶级领导权中心问题是()。A.无产阶级对军队的领导 B.无产阶级对
一住店客人未付房钱即想离开旅馆去车站。旅馆服务员揪住他不让走,并打报警电话。客人
二次衬砌的工施作业应隧道位移相对值已达到相对位移量的()以上后进行。A.20%
应暂缓结婚A.处女膜闭锁 B.强直性肌营养不良 C.血友病基因携带者 D.
最新回复
(
0
)