Project manager believes that modifying the project scope may provide added value for the customer. The project manager should ( ) .A.change the scope baselineB.contact the customer to determine if the change adds valueC.call a meeting of the change control boardD.change the project’ s objectives
选项
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project’ s objectives
答案
B
解析
项目经理认为修改项目范围可能要增加客户的费用,项目经理应该(联系客户去决定是否变更加钱)。
A、变更范围基线
B、联系客户去决定是否变更加钱
C、召开变更控制委员会议
D、改变项目目标
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302920.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Disasterstruck250millionyearsago,whentheworstdevastationintheeart
TheWesthasbeguntotakemorenoticeoftheEast.Thefifth【C1】______ofan
Thereisnothinglikethesuggestionofacancerrisktoscareaparent,esp
Ithaslongbeenknownthathigh-caloriefoodcanactasabalm(镇痛软膏)foran
在施工过程中,对承包人已完成的工程量的测量和计算,称为()。A.工程计量
尿本-周蛋白A.在10℃时沉淀,50℃时解溶 B.在20℃时沉淀,60℃时解溶
长期仰卧位的病人压疮的好发部位是A.髂前上棘 B.骶尾部 C.肩胛骨 D.
目前为提高城市供热系统的保证率,采用各供热分区联网的形式。各供热分区应保证有(
期货交易所在指定交割仓库时主要考虑的因素是指定交割仓库()。A.所在地区的生产
《医疗器械经营企业许可证》的有效期限为A.3年 B.5年 C.7年 D.9
最新回复
(
0
)