In project management,a ( ) is a list of a project’s milestones,activities,and deliverables,usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.A.scheduleB.WBSC.SOWD.charter
选项
A.schedule
B.WBS
C.SOW
D.charter
答案
A
解析
在项目管理中,(进度表)是一个项目的里程碑、活动和交付物的列表,通常还包括预期的开始日期和完成日期。这些项目往往是估计在资源配置方面,预算和时间依赖关系,联系和安排的活动。
A、进度表
B、WBS
C、SOW
D、项目章程
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302533.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thehighestlevelofqualitymanagement
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
Inprojectmanagement,a( )isalist
Ascheduleiscommonlyusedinprojectp
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Riskmanagement's( )istoassureunce
随机试题
______everywordofhisweretrue,whatactionwouldthecommitteewishtotake?
【B1】[br]【B6】A、formerB、returnedC、reversedD、regularC本题考查语篇知识。从上下文可以知道,这里讲的是睡
Sincethe1940s,southernCaliforniahashadareputationforsmog.Thingsar
砌体结构设计时,必须满足下列中的哪些要求? Ⅰ.满足承载能力极限状态 Ⅱ.满
新课程倡导基于反思的教师专业发展,波斯纳在1989年就提出了一个教师成长的公式,
正常成人骨髓象粒红比值是A.2~4:1B.1:0C.1:2~4D.3~5:0E.
下列哪项是颌下急性蜂窝织炎尽早切开的目的A.防止中毒 B.防止高热 C.防止
《汉谟拉比法典》是历史上已知的第一部比较完备的成文法典。你知道它出自于下列哪一文
企业购入需要安装的机器一台,价款100000元,增值税额按17%计算,运输费用
FIDIC《施工合同条件》中,对工程量增减变化较大需要调整合同约定单价不包括的条
最新回复
(
0
)