If the approved change requests have an effect on the project scope,then the corresponding component documents and cost baselines,and( )of the project management plan are revised and reissued to reflect the approved changes.A.developing baselines B.testing baselines C.schedule base lines D.ending baselines
选项
A.developing baselines
B.testing baselines
C.schedule base lines
D.ending baselines
答案
C
解析
如果批准的变更请求对项目范围的影响,那么相应的组件文件和成本基线,和进度基线的项目管理计划。修订再版反映批准的变更。(75) A.发展基线 B.测试基线 C.进度基线 D.结束基线
转载请注明原文地址:https://www.tihaiku.com/congyezige/2296001.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )istheapprovedversionofthetime-
ThePerformIntegratedChangeControlpr
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
ThePerformIntegratedChangeControl
TheperformIntegratedChangeContorlpr
Iftheapprovedchangerequestshavean
Changesmayberequestedbyanystakehol
Iftheapprovedchangerequestshavean
Changesmayberequestedbyanystakehol
随机试题
Inthe______halfofthe17thcenturythosecitiesbecameevenmoreprosperous.A、
A.刺激胃酸分泌 B. C.两者都是 D.两者都不是促胰液素的作用是(
某城市给水工程项目,该工程项目属大中型工程项目施工组织设计,设计单位组织有关单位
阅读下列说明和图。[说明]某公司欲开发招聘系统以提高招聘效率,其主要功能如下:1
下列()陈述描述了内部控制调查问卷。A.提供了控制系统实质方面的详细证据
公司制定股利政策应考虑的股东因素有( )。A.资本保全 B.企业积累 C.
某工程双代号时标网络计划如下图所示,其中工作E的总时差和自由时差为( )周。
A.单纯扩散 B.易化扩散 C.出胞作用 D.原发性主动转运 E.继发性
A. B. C. D.
电动机电流干燥法时,其电流大小宜控制在电机额定电流的( )。A.40%以内
最新回复
(
0
)