The perform Integrated Change Contorl process is the uitimste responsbilityof the (请作答此空) ,Although changes my be intitated verbally,they should be recorded in writtern form and entered into the ( ) syste.A.resource managerB.division managerC.functional managerD.projeet manager
选项
A.resource manager
B.division manager
C.functional manager
D.projeet manager
答案
D
解析
翻译:执行综合变更控制过程是(请作答此空)的首要责任,尽管口头上对变更进行了说明,但它们应以书面形式记录并输入( )系统。A. 资源管理员B. 部门经理C. 职能经理D. 项目经理
转载请注明原文地址:https://www.tihaiku.com/congyezige/2299520.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isameasureofscheduleperformance
Workperformanceinformationiscirculat
ThePerformIntegratedChangeControlpr
PerformQualityControlistheprocesso
hePerformIntegratedChangeControlpro
ThePerformIntegratedChangeControl
PerformQualityControlistheprocesso
Iftheapprovedchangerequestshavean
Manyoftheactivitiesperformedduring
Changesmayberequestedbyanystakehol
随机试题
Thecompanyislikelytobeprosecutesbecauseithasdumpedenvironmental!Haza
ARegularEuropeanbusinesstravellersviewtravellingoncommercialairlinesas
Ifthepopulationoftheearthgoesonincreasingatitspresentrate,there
【B1】[br]【B2】在not与be之间加to。nottoberudetohisguest这一不定式短语充当desire的后置定语。
[originaltext]W:(8)I’mlosingmysleep.Ifeeltiredandsleepyallthetime.
[originaltext]M:Hello.Doyouhaveanyapartmentsforrentrightnow?I’vebee
NaturalgasVehiclesKermittheFrogoncesaid,
回答隧道环境检测设备检验评定的提问。(2)环境检测器的灵敏度实测项目有()。
沥青路面车辙损害按长度计算,检测结果要用影响宽度()换算成面积。A.0.2m
可用口服补液方式治疗的是A.新生儿腹泻 B.腹泻伴重度脱水 C.腹胀明显
最新回复
(
0
)