Changes may be requested by any stakehol
Changes may be requested by any stakehol
admin
2022-08-02
69
问题
Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT manager B.project manger C.change control board D.project sponsor
选项
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
答案
C
解析
项目变更可以由执行经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过。(73) A.执行经理 B.项目经理 C.变更控制委员会 D.项目发起人
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295962.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Stakeholdermanagementreferstomanagin
Changesmayberequestedbyanystakehol
Stakeholdermanagementreferstomanagin
Changesmayberequestedbyanystakehol
随机试题
TherearepeopleinItalywhocan’tstandsoccer.NotallCanadianslovehoc
[originaltext]Oneofthegreatjoysofgardeningistoshareagardenwith
[audioFiles]audio_eufm_j63_001(20082)[/audioFiles]A、Sheistiredofdoinghomew
Thecoursewould(havebeenoffered)thisterm,butit(cancelled)becausetoof
[originaltext]W:Tony,wouldyouliketogoswimmingwithus?M:Thanks,buti
It'snosecretthatmostofusdon'tget
下列关于定性数据的图形表示方法,正确的有()。A.饼图主要用于总体中各组成部分所
关于人民群众和杰出人物在历史作用问题上,历史唯物主义认为( ) A.人民群众
1956年,毛泽东先后在中共中央政治局扩大会议和最高国务会议上作的《论十大关系》
(2018年真题)若纯粹利率为3%,通货膨胀补偿率为2%,某投资债券公司要求的风
最新回复
(
0
)