Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT manager B.project manger C.change control board D.project sponsor
选项
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
答案
C
解析
项目变更可以由执行经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过。(73) A.执行经理 B.项目经理 C.变更控制委员会 D.项目发起人
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295962.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Stakeholdermanagementreferstomanagin
Changesmayberequestedbyanystakehol
Stakeholdermanagementreferstomanagin
Changesmayberequestedbyanystakehol
随机试题
Inasense,thenewprotectionismisnotprotectionismatall,atleastnot
Thefunctionofgovernmentistosatisfythegenuinewantsofthemasses,andgo
[originaltext]W:Withthecompanyinsuchfinancialdifficulties,Iwonderwhat
Informedpublicdebatecriticaltofutureofgenomicmedicine
我国主要以( )作为划分行业的基本单位。A.机构单位 B.法人单位 C.活
小样本情况下,总体服从正态分布,总体方差未知,总体均值在置信水平(1-a)下的置
腹部实质性脏器手术的切口属于A.轻度污染伤口 B.可能污染伤口 C.污染伤口
如果基金的平均市盈率、平均市净率小于市场指数的市盈率和市净率,可以认为该股票型基
山楂、神曲有利于脂肪消化的原因是A:含有脂肪酶B:含有淀粉酶C:含有有机酸
下列属于超过一定规模的危险性较大的单项工程的是( )。A.集中线荷载15~20k
最新回复
(
0
)