首页
登录
从业资格
Perform Quality Control is the process o
Perform Quality Control is the process o
考试题库
2022-08-02
64
问题
Perform Quality Control is the process of monitoring and recording results*of executing the Quality Plan activities to assess performance and recommend necessary changes.() are the techniques and tools in performing quality control① Statistical sampling ② Run chart③ Control charts ④ Critical Path Method⑤ Pareto chart⑥ Cause and effect diagramsA.①②③④B.②③④⑤C.①②③⑤⑥D.①③④⑤⑥
选项
A.①②③④
B.②③④⑤
C.①②③⑤⑥
D.①③④⑤⑥
答案
C
解析
实现项目质量控制的方法、技术和工具包括统计抽样(Statistical sampling)、运行图 (Run chart)、控制图(Control charts)、帕累托图(Pareto chart),以及因果图(Cause and effect diagrams)等。关键路径法(Critical Path Method)是制定项目进度计划的方法,因此选C。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2299700.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thehighestlevelofqualitymanagement
( )isaprocessofdevelopingadocumen
Workperformanceinformationiscirculat
( )istheprocessofimplementingrisk
( )isaprocessofdevelopingadetail
以下关于项目变更控制委员会(ChangeControlBoard,CCB)
( )istheoutputofthequalityplannin
PlanQualityistheprocessofidentifyi
PerformQualityControlistheprocesso
随机试题
PROBLEMSFACINGPOTENTIALEXPORTERS1Inordertobesuccessful,
Signsofdeafnesshadgivenhimgreatanxietyasearlyas1798.Foralongt
Oneorperhapsmorepages______missing.A、isB、areC、hasbeenD、havebeenB题干大意
Tomtriedhisbesttokeepawake,buttheperformancewassoboringthathecoul
在Windows操作系统中,某主机运行()命令后显示的信息如下图所示,则该网
A.通阳散结,行气导滞B.散寒通阳,解毒散结,调经止痛C.通阳散结,疏肝解郁,宽
A. B. C. D.
TCP/IP体系结构中的TCP和IP所提供的服务分别为( )。A.链路层服务和
矿山工程进度拖延时,正确的事后措施包括有()。A.分析原因和影响工期程度 B.
患儿男,5岁。高热1天,第2天出疹,全身皮肤弥漫性充血发红,可见密集、均匀的红色
最新回复
(
0
)