问题 Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.A.Resource assignment matrix   B.Change control plan C.Project charter  D.Client organization chart

选项 A.Resource assignment matrix  
B.Change control plan
C.Project charter
D.Client organization chart

答案 B

解析 在项目执行的过程中你刚刚获得项目的控制权力,并且需要了解谁具有范围修正的权限,变更控制计划文件提供了该信息。 A.资源分配矩阵                  B.变更控制计划  C.项目章程                D.客户组织结构图