问题
( ) is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.A. Analogous estimatingB. Parametric estimatingC. Three-Point estimatingD. Bottom-Up estimating
选项
A. Analogous estimating
B. Parametric estimating
C. Three-Point estimating
D. Bottom-Up estimating
答案
A
解析
是一种使用来自类似活动或项目的历史数据来估算活动或项目的持续时间或成本的技术。
A、类比估算
B、参数估算
C、三点估算
D、自下而上的估算
转载请注明原文地址:https://www.tihaiku.com/congyezige/2298146.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()isaprojectmanagementtechniquefor
Theearnedvaluetechniqueisacommonly
Theearnedvaluetechniqueisacommonly
()isaprojectmangementtechniqueform
estimatingisatechniqueforestimating
Manyusefultoolsandtechniquesareuse
()estimatingisatechniqueforestimat
Estimatingactivity durationsusesinfo
The()techniqueinvolvesusingproject
()isoneofthetoolsandtechniquesof
随机试题
[originaltext]Charlie’sAngelssentAdamSandler’sdevilishnewcomedytopu
Oneofthemostinterestingofallstudiesisthestudyofwordsandwordor
Ourbodiesexperienceanebbandflowofenergythroughouttheday.Thisis
下列关于气胸的描述,正确的是A.单纯性气胸,立位胸片示外高内低致密影 B.MR
用100g锥测定土的界限含水率时,应按()确定土的塑限锥入深度。A.5mm
A.5~8岁 B.50岁 C.10~15岁 D.12岁 E.18岁恒牙龋
主动脉瓣狭窄的晚期,可见A.收缩压升高,脉压正常 B.脉压升高,收缩压正常
Heworkstenhoursaday,makesmoretha
适用于工作条件恶劣的介质,如氧气、甲烷、乙烯等,且特别适用于含纤维、微小固体颗粒
土坝坝面作业包含的工序有()。A.铺料 B.排水 C.整平 D.压实
最新回复
(
0
)