Estimating activity durations uses info
Estimating activity durations uses info
题库
2022-08-02
53
问题
Estimating activitydurations uses information on activity scope of ( ) , required resource types, estimatedresource quantities, and resource calendars.A.milestone B. baseline C.quality D. work
选项
A.milestone
B. baseline
C.quality
D. work
答案
D
解析
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295970.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
()isatechniqueforestimatingthedu
EstimateActivityDurationsistheproce
estimatingisatechniqueforestimating
()estimatingisatechniqueforestimat
Estimatingactivity durationsusesinfo
TheEstimateActivityResourceprocessi
Estimatingscheduleactivitycostsinvol
EstimateActivityDurationsistheprocessofe
随机试题
Thereportmanagedtogetan______interviewwiththePrimeMinister.A、extinctB、
Atfirstthechildrenwere______butasthemorningprogressedtheybegantolaug
Barbecuinghasbecomean【C1】______partofAmericanlife,asbarbecuegrill
公路工程竣工验收的条件不包括()。A.通车试运营3年以上 B.交工验收提
石材幕墙不宜采用( )。A.T形挂装系统 B.SE型组合挂装 C.背栓式
外周血网织红细胞增多,最常见于A.巨幼细胞性贫血 B.白血病 C.缺铁性贫血
(2012年)如果企业欲降低某种产品的盈亏临界点销售量,在其他条件不变的情况下,
某甲是间歇性精神病人。某日,某甲喝醉了酒,把某酒店老板打成重伤,在群众抓捕他时,
D给定图形拼合后所形成的图形为:
下列指标中,属于盈利能力分析的动态指标的是()。A.总投资收益率 B.内
最新回复
(
0
)