问题
EstimateActivityDurationsistheprocessofestimatingthenumberofworkperiodstocompleteindivitieswithestimatedresources.Thetoolsandtechnquesisnotincluding( ).A. expertjudgmentB. analogousestimatingC. requirementstraceabilitymatrixD. three-pointestimating
选项
A. expertjudgment
B. analogousestimating
C. requirementstraceabilitymatrix
D. three-pointestimating
答案
C
解析
转载请注明原文地址:https://www.tihaiku.com/congyezige/2294598.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
随机试题
Theschoolyeariswindingdown,butonefactionwithintheworldofeducati
—Hello,ProfessorWilliams.Thankyouforacceptingmyinterviewonculturaldiff
[originaltext]W:Hi,Sam,IhatetobotheryoubutIwonderifIcouldhaveaw
[originaltext]IntheUnitedStates,manypeopleoncelivedinlarge,two-and-th
Oftenpeopleassociatetheword"success"withabluepin-stripedsuitandt
一只“220V,100W”的灯泡工作时电阻为484Ω,拿一只这种灯泡测量其不工作
Breakfastisnotonlythemostimporta
房地产开发企业在领取营业执照后的多长时间内,应当到登记机关所在地的县级以上地方人
客户关系管理(CRM)系统将市场营销的科学管理理念通过信息技术的手段集成在软件上
男孩,5岁,水肿4天,气促1天,伴尿少,尿色深。尿常规检查:RBC++/高倍视野
最新回复
(
0
)