首页
登录
从业资格
( )estimating is a technique for estimat
( )estimating is a technique for estimat
admin
2022-08-02
85
问题
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.Parametric B.Analogous C.Three-point D.Expert judgment
选项
A.Parametric
B.Analogous
C.Three-point
D.Expert judgment
答案
B
解析
类比估计是一项使用类似的活动或项目的历史数据,来估计活动的时间或成本的技术。 (73) A.参数 B.类比 C.三点 D.专家判断
转载请注明原文地址:https://www.tihaiku.com/congyezige/2296017.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
()isaprojectmanagementtechniquefor
Thoseitemsareoftenestimatedinterms
Theearnedvaluetechniqueisacommonly
()isoneofthetoolsandtechniqueso
estimatingisatechniqueforestimating
allofthefollowingtoolsandtechnique
Manyusefultoolsandtechniquesareuse
()estimatingisatechniqueforestimat
Estimatingactivity durationsusesinfo
随机试题
WhichdayisLincoln’sBirthday?A、February12.B、February22.C、July4.D、Octobe
Theabilitytolaughatyourownflaws,weaknessesandblundershaslongbee
Inrecentyearn,Israeliconsumershavegrownmoredemandingasthey’vebeco
Anobviousstyle,easilyidentifiedbysomesuperficialquirk,isproperly(i)__
A.预防结核病的制剂 B.预防伤寒、副伤寒的制剂 C.预防乙型脑炎的制剂
关于证券公司柜台市场业务结算的说法正确的是()。 ①为柜台市场提供结算
过敏性接触性口炎主要是A.Ⅰ型变态反应 B.Ⅱ型变态反应 C.Ⅲ型变态
甲股份有限公司2020年有关所有者权益变动等的资料如下: (1)2020年7月
某电信公司针对新推出的3G上网卡业务,制定的资费方案如下 四种资费
在工程网络计划中,某项工作的最早完成时间与其紧后工作的最早开始时间之间的差值称为
最新回复
(
0
)