The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
选项
答案
B
解析
挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:()A.项目滞后B.项目超前C.项目超支D.成本有结余
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301714.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Theearnedvaluetechniqueisacommonly
Ethernetisthecommonlyusedlocalarea
Earnedvaluemanagement(EVM)integrates
()isaprojectmanagementtechniquefor
Aprojectmanagementtechniquethatisc
Theearnedvaluetechniqueisacommonly
Theearnedvaluetechniqueisacommonly
Theearnedvaluetechniqueisacommonly
Earnedvaluemanagement(EVM)integrates
随机试题
Anewbiotechnologyprocedurethatcouldbecomecommerciallyavailableinas
Tobeagoodteacher,youneedsomeofthegiftsofagoodactor:Youmustbe
REDOUBTABLE:A、mediocreB、permanentC、lucidD、unavoidableE、predictableA
泼水节(Water-SplashingFestival)是傣族(theDajminority)最隆重的传统节日。它通常在阳历(thesolar
含铁血黄素颗粒可见于尿中何种细胞A.红细胞B.中性粒细胞C.肾小管上皮细胞D.鳞
多尿是指24小时尿量超过( )。A.400ml B.800ml C.100
国内培训实行对口培训,培训对象主要是()。A:生产岗位的操作人员 B:技术人
定距尺度的计量结果可以( )。A.相加 B.相除 C.相乘 D.相减
由中国证监会负责监管的非银行金融机构不包括()。A.证券公司 B.期货公司
在组织机构的设置上,会员制期货交易所与公司制期货交易所的异同点有()。A:会
最新回复
(
0
)