首页
登录
从业资格
The earned value technique is a commonly
The earned value technique is a commonly
练习题库
2022-08-02
95
问题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .A.he project is ahead of its planned scheduleB.less work was completed than was planned tC.the cost overrun for work completedD.the cost underrun of performance to date
选项
A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date
答案
B
解析
转载请注明原文地址:https://www.tihaiku.com/congyezige/2299763.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprojectmanagementtechniquefo
Ascheduleiscommonlyusedinprojectp
Theearnedvaluetechniqueisacommonly
Ethernetisthecommonlyusedlocalarea
Ethernetisthecommonlyusedlocalarea
()isaprojectmanagementtechniquefor
Aprojectmanagementtechniquethatisc
Theearnedvaluetechniqueisacommonly
Earnedvaluemanagement(EvM)integrates
Ethernetisthecommonlyusedlocalarea
随机试题
Anewbiotechnologyprocedurethatcouldbecomecommerciallyavailableinas
Tobeagoodteacher,youneedsomeofthegiftsofagoodactor:Youmustbe
REDOUBTABLE:A、mediocreB、permanentC、lucidD、unavoidableE、predictableA
泼水节(Water-SplashingFestival)是傣族(theDajminority)最隆重的传统节日。它通常在阳历(thesolar
含铁血黄素颗粒可见于尿中何种细胞A.红细胞B.中性粒细胞C.肾小管上皮细胞D.鳞
多尿是指24小时尿量超过( )。A.400ml B.800ml C.100
国内培训实行对口培训,培训对象主要是()。A:生产岗位的操作人员 B:技术人
定距尺度的计量结果可以( )。A.相加 B.相除 C.相乘 D.相减
由中国证监会负责监管的非银行金融机构不包括()。A.证券公司 B.期货公司
在组织机构的设置上,会员制期货交易所与公司制期货交易所的异同点有()。A:会
最新回复
(
0
)