Earned value management(EVM) integrates
Earned value management(EVM) integrates
免费题库
2022-08-02
76
问题
Earned value management(EVM) integrates the scope baseline with the ()baseline,along with schedule baseline,to form the performance baseline,which helps the project management team assess and measure project performance and progress.A.qualityB.riskC.changeD.cost
选项
A.quality
B.risk
C.change
D.cost
答案
D
解析
挣值管理(EVM)将范围基线与(成本)基线以及进度基线集成在一起,形成性能基线,帮助项目管理团队评估和度量项目性能和进度。
A、质量
B、风险
C、变更
D、成本
转载请注明原文地址:https://www.tihaiku.com/congyezige/2298205.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thehighestlevelofqualitymanagement
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
ProjectIntegrationManagementincludes
( )managementincludesnegotiatingthe
TheProjectManagementTriangleisamod
Riskmanagementallowstheprojectmanag
()managementincludesnegotiatingthe
随机试题
WhowroteTheAmerican?A、HermanMelville.B、NathanielHawthorne.C、HenryJames.
He’soneofthemost______(bore)peopleI’veevermet.Heneverstopstalking
商业银行受理新客户贷款申请后,信贷业务人员通常要()。A.面谈访问进行前期调
证券分析师基于特定客户的立场,遵循忠实客户利益原则,向客户提供适当的证券投资建议
下列有关法律规则的说法中,哪一选项是错误的?()A.《民法总则》第40条规定:
薪酬结构设计是薪酬的( )两种薪酬有效性标准进行平衡的一种结果。A.内部差异性
(2014年真题)可转换债券的持有人具有在未来按一定的价格购买普通股股票的权利,
输入收款单。(用户名:101,账套:900,操作日期:2014年1月31日)20
厂区噪声水平调查测量点布置在厂界外( )处,间隔可以为50~100m,大型项目
某开发商以A地块的建设用地使用权作为向银行贷款的担保,确保近期还款,此担保方式属
最新回复
(
0
)