( )is a project management technique for
( )is a project management technique for
资格题库
2022-08-02
76
问题
( )is a project management technique for measuring projectPerformance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.A.Critica1 path method(CPM)B.Earned value management(CEV)C.Net present value method(NPVM)D.Expert judgment method(EJM)
选项
A.Critica1 path method(CPM)
B.Earned value management(CEV)
C.Net present value method(NPVM)
D.Expert judgment method(EJM)
答案
B
解析
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301744.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Humanresourcemanagementisthemanagem
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
( )managementincludesnegotiatingthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
Establishingaproject( )involveslis
Riskmanagement's( )istoassureunce
随机试题
Ifyouarelikemostpeople,yourintelligencevariesfromseasontoseason.
Inthesamewaythatachildmustbeabletomovehisarmsandlegsbeforeh
A------trackandfieldJ------roadraceB------cheerleaderK------platformdivi
固定式消防给水设备可以釆用由电动机驱动的消防泵组,也可以釆用由燃油发动机驱动的消
A.白芷 B.羌活 C.荆芥 D.紫苏叶 E.防风外感风寒,眉棱骨痛者,
证券分析师从业人员年检期间培训学时为( )。A.16学时 B.18学时 C
以下说法不正确的是:()。A.医药制造业的增速明显高于药械制造业 B.中
国际市场基本金属等大宗商品价格均以()计价。A:美元 B:人民币 C:
从长期看,关于成本的说法,正确的是()A.所有成本都是变动成本 B.所有成
根据《标准施工招标文件》,关于暂停施工的说法,正确的是()。A.由于发包人原因引
最新回复
(
0
)