首页
登录
从业资格
Estimating schedule activity costs invol
Estimating schedule activity costs invol
admin
2022-08-02
64
问题
Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of theA.project scope statement B.statement of work C.project management plan D.project policy
选项
A.project scope statement
B.statement of work
C.project management plan
D.project policy
答案
A
解析
估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本,成本估算包括设别和考虑各种成本计算方案。例如:在多数的应用领域,普遍在设计阶段多做些额外工作以降低在执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般是以货币单位表示,以利于在项目内和项目间进行比较,项目范围说明书描述了项目的商业要求、理由、需求和当前边界,它提供了关于在成本估算时必须考虑的项目需求的重要信息。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295903.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inprojecttimemanagement,activitydef
Theprojectscheduleismorethanadocu
Scheduledevelopmentcanrequiretherev
Theprojectscheduleismorethanadocu
果在一个课程注册系统中,定义了类CourseSchedule和类Course,并
Ascheduleiscommonlyusedinprojectp
Scheduledevelopmentcanrequiretherev
Scheduledevelopmentcanrequiretherev
()isatechniqueforestimatingthedu
EstimateActivityDurationsistheproce
随机试题
Hehas________thearmyfortenyearsandisnowanofficer.A、goneintoB、joine
PASSAGETHREE[br]Whatdoes"Heisanindividualwhorefusestobendhisback"
Inatelephonesurveyofmorethan2,000adults,21%saidtheybelievedthe
解:本题考查两个相互表示的向量组之间秩的关系。
下列关于炉外精炼的技术功能,说法错误的是( )。A.降低钢中硫、氧、氢、氮和非
下列关于交付估价报告的说法中,正确的有()。A.交付估价报告是房地产估价的
关于人力资源需求预测方法的表述,不正确的是()。A:设备看管定额定员法是按劳动
案例一(5): 第三次咨询:2016年3月9日 求助者:您好!上一次
下列融资方式中,需要通过证券市场卖债券进行融资的是( )。A.BOT B.A
知识点:VLDL 血浆脂蛋白VLDL的主要合成部位是 A.小肠粘膜细胞 B
最新回复
(
0
)