首页
登录
从业资格
Schedule development can require the rev
Schedule development can require the rev
免费题库
2022-08-02
56
问题
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.A.scope statementB.activity listC.project charterD.project schedule
选项
A.scope statement
B.activity list
C.project charter
D.project schedule
答案
D
解析
计划进展需要对持续时间和资源的评估和修改创建一个被核准的(74),它可以作为基线,有助于跟踪进展。
A. 范围说明 B. 活动列表 C. 项目章程 D. 项目计划
转载请注明原文地址:https://www.tihaiku.com/congyezige/2299734.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Ascheduleiscommonlyusedinprojectp
Scheduledevelopmentcanrequiretherev
Scheduledevelopmentcanrequiretherev
Theprojectscheduleismorethanadocu
TheDevelopmentofProjectManagementPl
TheSystemsDevelopmentLife Cycle(SDL
Scheduledevelopmentcanrequiretherev
Ascheduleiscommonlyusedinprojectp
Scheduledevelopmentcanrequiretherev
Theschedulemanagementplanisacompon
随机试题
TheChinesefairystoryFlyingtotheMoonnowturnstobetrue,withChina【
[originaltext]Manyoftheemployeesthinktheircareerpathandplansbegin
[originaltext]DeepSpringsisanAmericancollege.Itisanunusualcollege
按照水泥比表面积勃氏法,GB/T8074-2008中,两次透气试验的结果相差超过
发光强度系数的单位为cd·lx-1。()
同步能力验证计划是从材料中随机抽取子样,同时分发给参加者共同进行测试,这类计划能
共用题干 Scotland:ALandofWisdomInthe17
代表基金份额10%以上的基金份额持有人就同一事项要求召开基金份额持有人大会,而基
案例六: 一般资料:求助者,男性,41岁,高中毕业,已婚。 案例介绍:半年多
根据《环境噪声污染防治法》对可能产生环境噪声污染的工业设备的有关规定,使用固定的
最新回复
(
0
)