Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress.A.scope statementB.activity listC.project charterD.project schedule
选项
答案
D
解析
计划进展需要对持续时间和资源的评估和修改创建一个被核准的(),它可以作为基线,有助于跟踪进展。A.范围说明B.活动列表C.项目章程 D.项目计划
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301776.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
TheSystemsDevelopmentLifeCycle(SDLC
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
Theprojectscheduleismorethanadocu
Scheduledevelopmentcanrequiretherev
Theprojectscheduleismorethanadocu
TheDevelopmentofProjectManagementPl
Theprojectscheduleismorethanadocu
Ascheduleiscommonlyusedinprojectp
Theschedulemanagementplanisacompon
()includestheprocessesrequiredtoen
随机试题
5StepstoBecomingaBetterNetworkerWeal
ValmontIndustries,Inc.isaleadingproduceranddistributorofproduct
Youcanfindatablebelowshowingthepopulationchangefrom2010to2030,pr
Asmoredatafromaroundtheworldemergesandnewgenerationsofworkersse
电影院设计要求入场口与散场口:()A.分开设置 B.集中设置 C.合并设
健康促进测量指标不仅是针对健康状况,而且要针对人群的A.健康观念 B.社会环境
患者,女性,50岁。胆石症病史2年。3天前因腹痛、寒战、高热和黄疸发作,经门诊用
根据《公司法》的规定,股份有限公司董事会成员的人数最多是( )。A.5人 B
空气绝缘开关柜不应选用硅橡胶外套氧化锌避雷器。
能够从上述资料中推出的是: A.2008年上饶市初中和高中学校数在全
最新回复
(
0
)