首页
登录
从业资格
Schedule development can require the rev
Schedule development can require the rev
考试题库
2022-08-02
41
问题
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress.A.scope statementB.activity listC.project charterD.project schedule
选项
答案
D
解析
计划进展需要对持续时间和资源的评估和修改创建一个被核准的(),它可以作为基线,有助于跟踪进展。A.范围说明B.活动列表C.项目章程 D.项目计划
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301776.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
TheSystemsDevelopmentLifeCycle(SDLC
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
Theprojectscheduleismorethanadocu
Scheduledevelopmentcanrequiretherev
Theprojectscheduleismorethanadocu
TheDevelopmentofProjectManagementPl
Theprojectscheduleismorethanadocu
Ascheduleiscommonlyusedinprojectp
Theschedulemanagementplanisacompon
()includestheprocessesrequiredtoen
随机试题
Toooftenyoungpeoplegetthemselvesemploymentquitebyaccident,notknow
当110kV出线在()回及以上时直设置带旁路断路器的旁路母线。A.5
GB5101《烧结普通砖》将砖分为若干等级,当建筑物外墙面为清水墙时,下列哪种等
A. B. C. D.
A.CD3 B.CD19 C.POX D.MPO E.ALP急性髓细胞白
某工程队有50个工作效率相同的中级工人,完成一项修路任务需要20天。施工6天后,
3,5,9,16,28,()A.38 B.48 C.59 D.71
各种运输方式内外部的各个方面的构成和联系,就是( )。 A.运输系统
消防应急照明系统和疏散指示系统的组件安装需要满足相关规范的规定和要求,下列关于系
人在每一瞬间,将心理活动选择了某些对象而忽略了另一些对象。这一特点指的是注意的(
最新回复
(
0
)