首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
63
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
Whatdoesthemanoftendowithhisfriends?[br][originaltext]F:Whatdoyou
Whattimeisitnow?[br][originaltext]F:What’sthetimeonyourwatch?M:It
[originaltext]M:Wouldyoupleasebuythatbookforme?W:I’mnotgoingtothe
参与并取胜,这就是奥林匹克精神。它表现于弱者敢于向强者挑战,也表现于强者争取得更好的成绩。胜而又胜,优而更优,这种理想一直鼓舞着运动员奋力前进。他会尽其
The【B1】______ofclosed-circuittelevisionandothernewelectronicteaching
衡量社会生产力发展水平的主要标志是( )A.劳动资料 B.劳动对象 C.生
关于合剂叙述正确的是A.酊剂、流浸膏剂、醑剂与水混合时,应快速加入混合,以减少混
下列不符合“办事公道”这一行政道德规范的是()。 A.对不同的服务对象采取不
由于发包人责任造成承包人自有机械设备窝工,其索赔费按( )计算。A、台班单价
采用催化焚烧设施处理非甲烷总烃浓度为15000mg/m3的有机废气,焚烧后气体体
最新回复
(
0
)