首页
登录
从业资格
The project schedule is more than a docu
The project schedule is more than a docu
免费题库
2022-08-02
49
问题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record
选项
答案
B
解析
项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来()。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301715.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
( )isameasureofscheduleperformance
Thecustomerasksyourprojecttobecom
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
Aprojectmanageriscalledtoaninform
随机试题
[originaltext]KnowledgeisfreeontheInternetatasmallbutgrowingnumb
[originaltext]Myparentsranasmallrestaurant.Therestaurantwasopened
[originaltext]W:NewstudiesareprovingthatmoreandmoreAmericansarelivin
Iwillnotlendthebooktoyou______youcanreturnitintime.A、incaseB、so
[originaltext]W:Ihaven’tseenyouhereforacoupleofweeks.Haveyoustoppe
钢筋混凝土高层与多层结构体系,除()外均为常用体系。A.框架结构 B.网架
以下属于医学伦理学基本理论的是:A.美德论 B.后果论 C.道义论 D.公
根据以下资料,回答106——110题。 国际货币基金组织(IMF)近期公布
一般情况下,房地产估价和房地产评估可以不做区分。( )。
物业承接查验中出现质量问题的主要原因有()。A:施工单位不按规范施工B:给排水
最新回复
(
0
)