( )is aproject mangement technique for measuring project performance and proress.it has the ability to combine measurements of the project management triangle;scope.time and costs.A. Critica path method(CPM)B. Earned value mangagemengt(EVM)C. Net present value method(NPVM)D. Expert judgment method(EJM)
选项
A. Critica path method(CPM)
B. Earned value mangagemengt(EVM)
C. Net present value method(NPVM)
D. Expert judgment method(EJM)
答案
B
解析
本题考查的是挣值的相关知识。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2298708.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Aprojectmanagementtechniquethatisc
Aprojectmanagementtechniquethatisc
()isaprojectmangementtechniqueform
estimatingisatechniqueforestimating
allofthefollowingtoolsandtechnique
Manyusefultoolsandtechniquesareuse
Manyusefultoolsandtechniquesareuse
The()techniqueinvolvesusingproject
()isoneofthetoolsandtechniquesof
Manyusefultoolsandtechniquesareuse
随机试题
Inthepastdecadesomethirdworldcountrieshavesufferedfromacycleofdrou
WhowontheWorldCup1994footballgame?WhathappenedattheUnitedNations?H
Mountingevidencehasledastronomerstojustanimprobableconclusion;At
[img]2012q2/ct_eyyjsdz2010b_eyyjsdcloze_0151_20121[/img]Coffeeismadefrom
WhenDonaldOlayerenrolledinnursingschoolnineyearsago,hisfathertoo
相对于证券投资基金,股权投资基金具有的特点包括( )。 Ⅰ投资期限长、流动性
(共用题干)患者女,27岁。人工流产后2天,突发下腹痛。查体:体温38.9℃,宫
马斯洛强调学生的学习应该是A.意义学习 B.有意义学习 C.内在学习 D.
地球表面大约有70%的面积被水覆盖,水的总量约有13.6亿立方公里,其中淡水所占
紫外分光光度法用于含量测定的方法有A.校正因子法 B.归一化法 C.对照品比
最新回复
(
0
)