Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).A.fast tracking B.what-if scenario analysis C.resource leveling D.critical chain methoD.
选项
A.fast tracking
B.what-if scenario analysis
C.resource leveling
D.critical chain methoD.
答案
A
解析
进度压缩技术包括赶工和快速跟进。(74) A.快速跟进 B.假设情景分析 C.资源平衡 D.关键链法
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295966.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojectmanagementandsystemsengine
( )isaprojectmanagementtechniquefo
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
Theprojectscheduleismorethanadocu
随机试题
Fewgreatarchitectshavebeensoadamantintheirbeliefintheintegration
HowtoSucceedinYourLiteratureClassCollegeliteratu
Aswehaveseen,thereisnothingaboutlanguageassuchthatmakeslinguis
[originaltext]Snakesmaybefound.justabouteverywhereexcepttheNorthP
QDII基金可以有的行为( )。A.购买不动产 B.购买房地产抵押按揭 C
男,36岁。突起昏迷,四肢瘫痪,双侧瞳孔针尖样缩小。其最可能的疾病是A:额叶出血
药检室负责制剂配制全过程的检验,其主要职责不包括A.制定质量管理组织任务、职责
下列关于中国银行业协会的表述,正确的是()。A、最高权力机构是委员大会 B、
某土方工程招标工程量清单中,土方开挖工程量为600m3。施工过程中,由于设计变更
最新回复
(
0
)