In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。A.scheduleB.activityC.PlanD.contractor
选项
A.schedule
B.activity
C.Plan
D.contractor
答案
A
解析
在项目管理中,( )是项目的里程碑、活动和交付物的列表,通常包括开始和完成日期。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2299731.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
Humanresourcemanagementisthemanagem
Inaprojectplan,whentheprojectmana
( )managementincludesnegotiatingthe
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Riskmanagement's( )istoassureunce
随机试题
WhichofthefollowingunderlinedphrasesisINCORRECT?A、Thishouseisthreetim
ComplaintDearSir/Madam,Aftercarefulexamin
TopicOnAcademicCheatingForthispart,youareallowed30minutestowr
Brownbreadandbutter______usuallyeatenwithsmokedsalmoninthewest.A、isB、
Accordingtotheauthor,Tolstoy’sabilitytowrite______.[br]Ourabilityto
气候炎热的地区,设置哪种形式的外遮阳能够有效地阻止夏季的阳光通过南向的窗口进入室
足太阴脾经的络穴是A、隐白 B、太白 C、公孙 D、地机 E、三阴交
2020年1—4月份,规模以上煤炭开采和洗选业营业成本比石油和天然气开采业约
在面试中,重要而关键的基本功包括( )。A.“望” B.“问” C.“听”
贯通测量的技术工作内容和要求,错误的是()A.应保证原始资料的可靠性和起算数据的
最新回复
(
0
)