Project work packages are typicallydecomposed into smaller components called activities to provide a basis for ( ) , scheduling, executing, andmonitoring and controlling the project work.A.reviewing B.estimating C.auditing D.expecting
选项
A.reviewing
B.estimating
C.auditing
D.expecting
答案
B
解析
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295956.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
Projectmanagerbelievesthatmodifying
Establishingaproject( )involveslis
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Aprojectmanageriscalledtoaninform
Theprojectmanagermustmaintainaneff
随机试题
[img]2012q1/ct_ebecflj_ebfllistbb_0273_20121[/img][br][originaltext]Woman:Go
[originaltext]Faces,likefingerprints,areunique.Didyoueverwonderhow
孕妇张某,28岁,GP,孕37周,凌晨4:00突感有较多液体自阴道流出急诊住院,
在个人住房贷款中,一般规定贷款成数为()。A:50% B:60% C:70%
A.过点(1,-1,0),方向向量为2i+j-k B.过点(1,-1,0),方
材料1:2007年上半年,猪肉价格上涨较快。温家宝总理2007年5月26日到陕西
某个人或经济组织的行为活动影响了他人或经济组织,却没有为之承担相应的成本或没有获
在社会平均利润率不变的的情况下,利率高低取决于()。 A.通货膨胀率
sx表示A.总体均数 B.个体变量值的离散程度 C.样本均数 D.样本均数
胸痛的病因
最新回复
(
0
)