问题
Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an elementA.cost management planB.risk management planC.soope management planD.management schedule
选项
A.cost management plan
B.risk management plan
C.soope management plan
D.management schedule
答案
D
解析
转载请注明原文地址:https://www.tihaiku.com/congyezige/2299704.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Ascheduleiscommonlyusedinprojectp
Theprojectbudgethasbeenfinalized.Ad
WhichofthefollowingProjectScopeMan
Aprojectmanageriscalledtoaninform
Theprojectscheduleismorethanadocu
Theprojectmanagermustmaintainaneff
( )describes,indetail,theproject’
随机试题
Whatwill______leadto?A、thepolicyofthegovernment’sB、thispolicyoftheg
Forthispart,youareallowed30minutestowriteashortessaybasedonthe
这些年来,教育和民间机构(non-governmentinstitution)组织了不少以孝道(filialpiety)为主题的活动。一些地方高调(hi
Judgingfromrecentsurveys,mostexpertsinsleepbehavioragreethatthere
Asunflowerisasunflower.Amobilephoneisamobilephone.Butcanyou【S1
中医医疗机构从事中医医疗活动,应按规定办理审批手续,取得()A.医疗机
下列有关环境容纳量的叙述,正确的是()。A.改变环境条件,K值一定不变 B
2020年12月,全国中心城市客运量的同比减少率与同年1月相差:A.不到
Passage8 Theveryloansthataresuppo
对于实行会员分级结算制度期货交易所的非结算会员,监控中心应当将其申请和注销客户交
最新回复
(
0
)