问题
( )the process of determining,documenting,and managing stakeholder needs and requirements to meet Project objectives.A.Plan Scope ManagementB.Collection RequirementsC.Validate ScopeD.Control Scope
选项
A.Plan Scope Management
B.Collection Requirements
C.Validate Scope
D.Control Scope
答案
B
解析
(收集需求)确定、记录和管理利益相关者需求和要求以满足项目目标的过程。
A.规划范围管理
B.收集需求
C.确认范围
D.控制范围
转载请注明原文地址:https://www.tihaiku.com/congyezige/2298491.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
()istheprocessofmonitoringthest
()includestheprocessforincorporat
( )isaprocessofmonitoringthestatu
Managingriskanddocumentingthemisve
PlanQualityistheprocessofidentifyi
()istheprocessofidentifyingindivi
Integration()istheprocessofverify
The()processanalyzestheeffectofrisk
Managingriskanddocumentingthemisve
Agoalofthe()processistodetermin
随机试题
PresidentCoolidge’sstatement,“ThebusinessofAmericaisbusiness,”still
Theworldhasneverbeenmorecloselyandintricatelyconnected.Ourbehavio
Theprocessbymeansofwhichhumanbeingscanarbitrarilymakecertainthin
Thepassagegivesageneralexplanationaboutthebenefitsofacross-culturalm
以下选项中,属于项目法人完成工程建设任务凭据的是()。A.竣工证书 B.
该省2009-2013年GDP的年平均增长率约为:() A.17.6%
有关调查问卷的基本内容,下列说法错误的是( )。 A.说明词是开始询问前的导
1993-91.憎寒壮热,头痛项强,肢体酸痛,无汗,鼻塞声重,咳嗽有痰,胸膈痞
假设英镑兑美元的即期汇率为1.4753,30天远期汇率为1.4783,这表明英镑
一住店客人未付房钱即想离开旅馆去车站。旅馆服务员揪住他不让走,并打报警电话。客人
最新回复
(
0
)