( )is the process of monitoring the status of the project to update the projects costs and managing changes to the cost baseline.A.Control costsB.Costs udatesC.Validate scopeD.Monitor communications
选项
A.Control costs
B.Costs udates
C.Validate scope
D.Monitor communications
答案
A
解析
()是监控项目状态以更新项目成本和管理成本基线变更的过程。
A、控制成本
B.、成本费用
C.、有效性范围
D.、监控通信
转载请注明原文地址:https://www.tihaiku.com/congyezige/2303804.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isaprocessofdevelopingadocumen
( )contributestomonitoringanddatac
( )istheprocessofimplementingrisk
( )isaprocessofdevelopingadetail
Validatescopeistheprocessofformali
Agoalofthe()processistodetermin
Integration()istheprocessofverify
The()processanalyzestheeffectofrisk
PlanQualityistheprocessofidentifyi
Integration()istheprocessofveri
随机试题
Onedayateacherwasgivingalessontotileboysandgirlsinherclass.Thet
TheWorldHealthOrganizationreportedtheenvironmentalhealthrisks,NOTinclu
A—toholdameetingE—finalsittingB—workingpartyF—formalsittingC—meetingi
Allthermalradiationfromaplanetarysurfaceabsorbedbyatmosphericgreenhous
AnncalledRogerto[br][originaltext]M:Hello.W:Hello,Roger?ThisisAnn.
“4”字试验的意义是:A.评估髋关节 B.评估骶髂关节 C.评估肩关节半脱位
促使潜在客户变为现实客户的策略有()。(2011年真题)A.为客户提供专业咨
近代社会以来,使医医关系发生重大变化的主要因素是()A.科学技术的进步B.医学
某窗间墙尺寸为1200mm×370mm,如图4-2所示,采用MU10砖和M2.5
(2017年真题)甲施工企业3月1日向乙供应商发出采购单购买一批建材,要
最新回复
(
0
)