Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( ).A.project management planB.project baselineC.risk response planD.risk baseline
选项
A.project management plan
B.project baseline
C.risk response plan
D.risk baseline
答案
A
解析
风险管理和记录他们是非常重要的项目规划过程。你的过程中确定主要风险,包括限制和假设,并计划和应急反应。这些细节将列入项目管理计划中。 A选项:项目管理计划;B选项:项目基准;C选项:风险应对计划;D选项:风险基准。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2302523.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Managingriskanddocumentingthemisve
Managingriskanddocumentingthemisve
Managingriskanddocumentingthemisve
( )istheprocessofmanagingprocureme
()istheprocessofdocumenting,analy
()istheprocessofdocumenting.Anal
随机试题
Aswementionedearlier,thereisawidevarietyofsportsactivitiesavaila
Theideathat"parentsdon’tmatter"—shorthandfortheviewthathowparent
混凝土的收缩对钢筋混凝土和预应力钢筋混凝土结构构件产生影响,以下叙述中错误的是:
A.清热解毒 B.止痢杀虫 C.化瘀利尿 D.固精缩尿 E.涩肠止泻仙鹤
A.蜡丸B.蜜丸C.水丸D.滴丸E.浓缩丸在体内不溶散,仅缓缓释放药物,可以减轻
在核实货币资金收支截止期时,审计人员发现被审计单位经常会采取下列做法,其中属于高
某国经济以农业为主,2001年遭受百年不遇的大旱,国际有关组织号召各国人民向该国
主要投资于风险相对较高的各类资产,基础资产收益波动较大,一定程度上将影响客户投资
(2018年真题)采用全寿命期费用法进行设计方案评价时,宜选用的费用指标是(
施工企业从银行借款50万元用作工程的投标保证金,该借款产生的利息属于( )。A.
最新回复
(
0
)