问题
All of followings should be done by the project manager during project control except ().A.Determine the a change has occurredB.Ensure that a change is agreedC.Make sure all changes are approved by managementD.Manage changes as they occur
选项
答案
B
解析
译文:项目经理不应该在项目控制过程中执行的工作是()。 A)确定变更已经发生 B)确保变更已达成共识 C)确保所有变更都获得管理层批准 D)在变更发生时,对变更进行管理
转载请注明原文地址:https://www.tihaiku.com/congyezige/2301727.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
Alloffollowingsshouldbedonebythe
随机试题
[originaltext]L:Weacceptbothcashandcreditcard,butitwillbesuchasma
Entertheinformationage.Informationistherawmaterialformanyoftheb
[A]Weapplyforcreditformanyreasons—maybeit’stobuyanewcar,house,comp
PurposesofArtI.AvehicleforreligiousritualThe【T1】_____:primarypatr
A. B. C. D.
下列行为中,构成不正当竞争的是() Ⅰ.基金管理公司A为了销售基金,开展"零
口腔颌面部最常见的感染病原体是A:单纯需氧菌感染 B:单纯厌氧菌感染 C:需
根据建标[2013]44号文件,属于措施费的有()。A、工程排污费 B、检验
可结婚,但限制生育A.处女膜闭锁 B.强直性肌营养不良 C.血友病基因携带者
关于施工质量的影响因素,下列说法正确的是()。A.材料质量是工程质量的基础 B
最新回复
(
0
)