()is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.A.PERTB.AOAC.WBSD.PDM
选项
A.PERT
B.AOA
C.WBS
D.PDM
答案
D
解析
(73)用于关键路径法,是用于编制项目进度网络图的一种方法,它使用方框或者长方形(被称作节点)代表活动,它们之间用箭头连接,显示彼此之间存在的逻辑关系。A.PERT B. AOAC. WBS D. PDM
转载请注明原文地址:https://www.tihaiku.com/congyezige/2299669.html
本试题收录于:
中级 系统集成项目管理工程师题库软件水平考试初中高级分类
中级 系统集成项目管理工程师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
()isamethodusedinCriticalPathMeth
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
Projectselectionmethodsinvolvemeasur
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Peoplesometimeswonderabouthowtoensurefamily’sfinancialwell-being.F
WhichAttributesofaFoodProductareMostImportanttoConsumersA)Th
Inthe1960sPopmusicunderwentarevolutionwhentheBeatlesbecameworldfamo
借款人能否按时足额偿还贷款本息,根本上要依靠借款人及其家庭的收入来源,或者其他的
依照《药品经营质量管理规范》,不符合药品零售企业药品陈列要求的情形有A.按药品的
A.较长时间暴露于强噪声,致使听阈上升超过15~30dB,脱离后需数小时至几十小
下列关于简化的经济增加值计算的说法中,不正确的是()。A.经济增加值=税后
高层建筑给水及排水铸铁管的柔性连接应采用()。2014A.石棉水泥密封 B.橡
某市政工程的网络计划图如下,其合理的合同工期应是()个月。A、6 B、8 C
取得建造师资格证书并经()后,方有资格以建造师名义担任建设工程项目施工的项目经理
最新回复
(
0
)