PDM is a method of constructing a project schedule network diagram that uses boxesor rectangles, referred to as nodes, to represent activities and connects them with arrows thatshow the dependencies.This method includes following types of dependencies or precedence relationships:F-S, the initiation of the successor activity, depends upon the completion of thepredecessor activity.() , the initiation of the successor activity, depends upon the initiation of thepredecessor activity.A.F-S B.F-F C.S-F D.S-S
选项
A.F-S
B.F-F
C.S-F
D.S-S
答案
D
解析
PDM是以一种方块或矩形(或称为节点)来表示活动,并将它们用表示依存关系的剪线链接起来,以构建项目进度网络图的方法。这种方法包括了下列依存或前导关系:完成---开始(F-S),后续活动的开始依赖于前置活动的完成。开始---开始(S-S),后续活动的开始依赖于前置活动的启动。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295913.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Inprojectmanagementandsystemsengine
Inaprojectplan,whentheprojectmana
ProjectIntegrationManagementincludes
Toensuretheprojectteamprovidesthe
TheProjectManagementTriangleisamod
Theprojectbudgethasbeenfinalized.Ad
WhichofthefollowingProjectScopeMan
Theprojectmanagermustmaintainaneff
随机试题
•ReadthetextbelowaboutITtraining.•Inmostofthelines(41-52)thereis
Whatisthe(deep)______ofthelakehere?depth本题测试的是词性转换。全句的意思是:“这个湖有多深?”构成名词的
Mycousinlikeseatingverymuch,butheisn’tvery______aboutthefoodheeat
正常人每日需能量为A、5000kJ B、6325kJ C、7535kJ D
企业自由现金流(FCFF)的表达公式是()。A.FCFF=利润总额(1-税率)
某县(省直接管辖)县医院发生医疗事故争议,需进行医疗事故技术鉴定,按照《医疗事故
A.水溶液型注射剂 B.混悬型注射剂 C.乳剂型注射剂 D.注射用无菌粉末
下列作品和作者对应正确的是()。A.《农政全书》——宋应星 B.《伤寒杂病
A.补益肝肾 B.滋肾养肝 C.滋阴补肾 D.泻火解毒 E.益气养阴障眼
慢性支气管炎急性发作期治疗最主要的措施是A.止咳祛痰 B.低流量吸氧 C.解
最新回复
(
0
)