首页
登录
从业资格
Project schedule management is made up o
Project schedule management is made up o
考试题库
2022-08-02
60
问题
Project schedule management is made up of six management processes including:activity definition, activity sequencing,( ) , and schedule control by order.A.activity duration estimating, schedule developing, activity resource estimatingB .activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
选项
A.activity duration estimating, schedule developing, activity resource estimating
B .activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
答案
B
解析
项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制定进度计划及进度控制六个步骤。
以上六个步骤具有先后顺序,因此选择“活动的资源估算”activityresourceestimating、“活动历时估算”activitydurationestimating、制定进度计划scheduledevelopment,所以选B。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2296949.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theproject()processesinclude:dev
Thehighestlevelofqualitymanagement
Thecustomerasksyourprojecttobecom
Inprojecttimemanagement,activitydef
Qualitymanagementensuresthatanorgan
Configurationmanagementisfocusedont
( )isaprojectmanagementtechniquefo
Toensuretheprojectteamprovidesthe
数据库管理系统(DatabaseManagementSystem)是一种操纵
TheProjectManagementTriangleisamod
随机试题
Recently,astudentusedhisPersonalDigitalAssistant(PDA)tofilmafema
Takeagood,longlookatthenewspaperyou’rereading.Whatcoulditbeuse
数字出版的主要特征有()等。A.内容生产数字化 B.管理过程数字化 C
当用钢筋牌号是HRB335的材料进行帮条焊和搭接焊,可用E4303焊条进行焊接。
肢体痿软日久,食少纳呆,腹胀便溏,面浮不华,神疲乏力者治疗时除选主穴外还可配用A
A.烘干法 B.甲苯法 C.薄层色谱法 D.减压干燥法 E.高效液相色谱
修复前一般不主张手术切除的是A:尖锐的骨突、骨尖和骨嵴 B:下方形成较大倒凹的
拌制混凝土选用石子,要求连续级配的目的是( )。A.减少水泥用量 B.适应机械
关于现金流量绘图规则的说法,正确的有()。A.箭线长短要能适当体现各时点现金流
工程竣工技术资料的移交必须严格管理,按()执行。A.合同 B.施工组织设
最新回复
(
0
)