首页
登录
从业资格
During planning you sit down and estimat
During planning you sit down and estimat
题库
2022-08-02
81
问题
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario ( ) .A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate;should be the same as the customer's reqhired completion date
选项
A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate;should be the same as the customer's reqhired completion date
答案
B
解析
当你计划坐下来,估计每个任务所需的时间和总他们的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是
B选项:团队不需要创建估算,不需要用到网络图
转载请注明原文地址:https://www.tihaiku.com/congyezige/2412589.html
本试题收录于:
中级 信息系统监理师题库软件水平考试初中高级分类
中级 信息系统监理师
软件水平考试初中高级
相关试题推荐
企业系统规划(BusinessSystemPlanning,BSP)的实现步
Workaroundsaredeterminedduringwhich
Onetoolthatisusefulduringbothanal
Duringplanningyousitdownandestimat
Duringtheinstallationofthegroove,t
Duringtheimplementationoftheproject
Duringtheinstallationofthegroove,th
()Estimatingcurrentprojectcostsbya
Duringtheimplementationoftheproject
随机试题
TheDragonBoatFestival,the5thdayofthe5thlunarmonth,hashadahistory
Thereisnodenyingthatourworldisbecomingmoreandmoredeveloped.Due
CATVisashortwayofsaying"communityantenna(天线)television".But"cable
魏老师在课堂教学中,要求学生运用学具,通过拨动钟面上的时针、分针和秒针来认识时间
在一个密闭的空间里,下列哪种说法正确?( )A.空气温度变化与相对湿度变化无关
某在用预应力混凝土T梁桥,跨径组合为3×30m,每跨设置9片T梁,经调查所有T梁
从资产负债管理的角度,风险管理经历了四个阶段。()。
胜利建筑公司注册商标于2013年12月31日到期,下列说法中正确的是()
甲上市公司(以下简称“甲公司”)于2008年4月1日在上海证券交易所上市。甲公司
通过减少反射波接收,提高微波通信质量的措施有()A.利用合适的地形地物
最新回复
(
0
)