The creation of a work breakdown structure(WBS)is the process of( )the major project deliverables.A.subdividingB.assessingC.planningD.integrating
选项
A.subdividing
B.assessing
C.planning
D.integrating
答案
A
解析
创建工作分解结构是分解项目可交付物的过程。
选项A是分解,选项B是估算,选项C是计划,选项D是整合。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2296803.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Theworkbreakdownstructure(WBS)hasb
Theworkbreakdownstructurecomprises
heworkbreakdownstructure(WBS)hasbe
heworkbreakdownstructurecomprisesse
Theworkbreakdownstructure(WBS)hasb
Theworkbreakdownstructurecomprisess
heworkbreakdownstructurecomprisesse
Thecreationofaworkbreakdownstructu
Thecreationofaworkbreakdownstructu
随机试题
China’s______culturalheritageshouldbebetterprotectedthroughincreasedeffo
[originaltext]Host:Welcometotoday’sshow,"Thewomenofmyvillage."Inthis
[originaltext]Jerusalem,Jan.27.MarkSokolowescapedwithoutinjuryfromt
[originaltext]Mr.Jones:Whatmaterialswereusedforroadsurfacesduringthe
人称“曲状元”的元代散曲作家是()A.王实甫 B.关汉卿 C.郑光祖
训练中运动负荷越大越好。()
未搞清地质情况就仓促开工,边设计边施工,无图施工,不经竣工验收就交付使用等,这是
经济周期一般分为()几个阶段。 ①增长期 ②繁荣期 ③衰退期 ④复苏期
访谈是社会工作定性研究的重要方法,社会工作者小林的访问对象是某个情况很复杂的问题
位于某市郊区的物流公司,占地面积共计20000平方米,其中:办公区占地1
最新回复
(
0
)