2022-08-02
34
问题
The strategies for handling risk comprise of two main types:negative risks, and positive risks.The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies( ),Transfer ,Mitigate .A.ChallengeB.ExploitC.AvoidD.Enhance
选项
A.Challenge
B.Exploit
C.Avoid
D.Enhance
答案
C
解析
风险应对策略包括两种类型:负面风险的应对策略和正向风险的应对策略:风险应对计划的目标是最小化威胁,并且最大化机会。处理负面风险有三种典型的战略:回避、转移和减轻。
选项A是挑战,选项B是开发,选项C是避免,选项D是提高。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2296800.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Severalriskresponsestrategiesareava
Theworkbreakdownstructurecomprises
Severalriskresponsestrategiesareavai
heworkbreakdownstructurecomprisesse
Theworkbreakdownstructurecomprisess
Severalriskresponsestrategiesareavai
heworkbreakdownstructurecomprisesse
Thestrategiesforhandlingriskcompris
Therearestrategiestypicallydealwith
Thestrategiesforhandlingriskcompris
随机试题
[originaltext]W:Whatarethesethingsinoursuitcase?Therearen’tanytoysa
OneofourmainargumentisthatweinWesterncountriesactually【
Inrecentyearsanewfarmingrevolutionhasbegun,onethatinvolvesthe【C1
2018年6月19日,十三届全国人大常委会第三次会议在京举行,会议初次审议了个人
共用题干 第二篇Don'tCountonDungConservation
下列作用中巴比妥类具有而苯二氮类没有的是A:镇静、催眠 B:抗焦虑 C:抗惊
事业单位的无形资产转让收入一般应计入()。A.预算外资金收入B.事业收入
下列属于施工进度控制组织措施的是( )。A.明确工程现场进度控制人员及其分工
根据《建设工程工程量清单计价规范》(GB50500—2013),关于工程量清单编
关于法人的说法,正确的是()。A.法人以其登记注册地为住所 B.企业法人
最新回复
(
0
)