首页
登录
职称英语
Wolfe Constructions 121 Fifteent
Wolfe Constructions 121 Fifteent
游客
2025-06-17
30
管理
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects. [br] Which of the following sentences can be inferred from the report?
选项
A、The reporter will dismiss the subcontractor sooner or later.
B、It will probably need more crew when dealing with the work indoors.
C、The work will fall farther behind if there is no extra electricians being added.
D、The framing, roofing, and siding is likely to have been finished by the middle of October if weather permitted.
答案
C
解析
转载请注明原文地址:https://www.tihaiku.com/zcyy/4122556.html
相关试题推荐
WolfeConstructions121Fifteent
WolfeConstructions121Fifteent
WolfeConstructions121Fifteent
WolfeConstructions121Fifteent
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate:A
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate:A
To:evan.bearden@avesmail.comFrom:sales@raptorconstructionsupplies.comDate:A
随机试题
Whatisthepositionwantedintheadvertisement?__________________________
Readashortpassageandlistentopartofalectureonthesametopic.A
Therearesomestepsyoucantakeyourselftoavoidcatchingacold.Contrar
磷酸戊糖途径的真正意义在于产生()的同时产生许多中间物(如核糖等)。
患者,女性,73岁。非胰岛素依赖型糖尿病史28年,近6年出现蛋白尿及高血压,近2
患者双下肢水肿,颈静脉怒张,肝一颈静脉回流征阳性,其最可能的病因是A.重症肝炎
(2019年真题)对某车用乙醇生产厂房进行防火检查,下列防火检查结果中,符合现行
加权平均法属于薪酬调查数据分析中的( )。A.数据排列法 B.趋中趋势分析
简述无领导小组讨论题目的类型、设计原则和流程。
下列资料中,可以作为招标工程量清单编制依据的有()。A、建设工程设计文件 B
最新回复
(
0
)