You will hear a speaker giving a group of managers advice on how to run a project.
As you listen, for questions 1-12, complete the notes using up to three words or a number.
After you have listened once, replay the recording.
RUNNING SUCCESSFUL PROJECTS
1 It is important to allow sufficient time for the______
2 Make sure that you establish a ______that is both sensible and manageable.
3 Always focus on the______situation.
4 Persuade your staff of the value of______to the project.
5 Competent______is important for monitoring the project.
6 Keeping staff informed will enable them to understand the______ they have made.
7 Meetings with staff from different departments may ______the project.
8 Ensure that you______when things go wrong.
9 You need to be ready to adapt if your client’s______are modified.
10 Encourage as much______as possible.
11 Be prepared to______as the market shifts.
12 Hire people who can be easily______if necessary. [br]
Woman: Um, OK, er, can I have your attention, please? Thanks. Now, er, people ask me ’how do I know if a project is good and, if so, how do I then keep it on track?’ Well, there are no magic formulas, but I do have a few tips for choosing and managing projects that I’d like to share with you today.
First of all, choose carefully! Your project needs to be large enough to be worthwhile and one in which your basic skills will enable you to succeed. This means sifting through proposals very carefully, and so it’s essential that you allocate enough hours to the selection process. When you’ve done that, you need to work out how long the project will take. It’s pretty tough to maintain a project’s freshness and flexibility, so you don’t want it running on too long -therefore, you need to set a sensible, manageable timescale.
When you start, you need to think about how your project will be better than the last one, and this means you should constantly keep the customer’s circumstances in mind and think about what they want. Employees will be enthusiastic about the project if you emphasise how important it is. So you should aim to convince them of how crucial teamwork is, and if you can do that, you’re more likely to get the best results. Also, good managers have a constantly updated picture of the project performance, and to achieve this, you need to be efficient at record-keeping.
As the project gets going, you should always keep employees informed and involved in what’s going on, so that they understand any constraints. At the same time, this will help them to appreciate the progress being made. And try meeting across boundaries. In well-managed projects, you’ll find that any meetings that are held are not exclusive to the project workers, but include people from different disciplines who work in the same organisation. These ’outsiders’ may come up with fresh approaches, which can speed up the whole project.
Now, encountering problems is almost inevitable; you need to recognise that and deal with them. To do this successfully, you need to share information about anything which is not going well. This will allow you to make decisions quickly and minimise any big changes. These may come as a result of the customer altering their requirements. It’s vital to be able to adjust to these developments, so make an attempt to be as flexible as you can in your dealings with them.
The prospect of success rises when those involved are consciously trying to do better than any other businesses or even past practices within their own company, so it’s important to breed competitiveness - the more the better if you want to get the best result.
And finally, don’t forget that companies that appear to be doing well all the time owe their success, in part, to a willingness to diversify when the market moves or alters, or as they recognise where they can make a better contribution. And, when you’re contemplating a risky project, make sure you employ people who have several skills. This means they could be transferred if the original project doesn’t succeed.
Well, er, I hope that’s helped. Um, now, if anybody has any questions . . .
[pause]
Now listen to the recording again.
[pause]
That is the end of Part One. You now have 20 seconds to check your answers.
选项
答案
SPEED UP / ACCELERATE
解析
转载请注明原文地址:https://www.tihaiku.com/zcyy/4100213.html
相关试题推荐
Youwillhearadiscussionbetweentwomanagers,KathyandDuncan,whoworkint
Youwillhearadiscussionbetweentwomanagers,KathyandDuncan,whoworkint
Youwillhearadiscussionbetweentwomanagers,KathyandDuncan,whoworkint
Youwillhearadiscussionbetweentwomanagers,KathyandDuncan,whoworkint
Youwillhearfiveseniormanagerstalkingaboutwhytheircompaniesselectedne
Youwillhearaspeakergivingagroupofmanagersadviceonhowtorunaprojec
Youwillhearaspeakergivingagroupofmanagersadviceonhowtorunaprojec
Youwillhearaspeakergivingagroupofmanagersadviceonhowtorunaprojec
Youwillhearaspeakergivingagroupofmanagersadviceonhowtorunaprojec
Youwillhearaspeakergivingagroupofmanagersadviceonhowtorunaprojec
随机试题
PRIMERECRUITMENTEmploymentrecordExampleSurname:LamertonEmail:【L1】_______
世界卫生组织和一些非政府组织于1999年2月发起"视觉2020,享有看见的权利"
下列不属于《旅游投诉处理办法》确定的,标准旅游投诉管辖地是:()。A.旅游合同
以下事项中,需要聘请保荐机构保荐的有( )。 Ⅰ.首次公开发行股票 Ⅱ.创
下列叙述正确的是: A所有地图的方向判别的方法都是“上北下南,左西右东”
“敬”有恭敬之意,有慎重、郑重之意,还有警惕、戒备之意。儒家强调要“执小敬”、“
根据《环境保护法》,关于按日连续处罚,下列哪一选项是错误的?A.金杉公司违法排放
案例九: 一般资料:求助者,男性,28岁,某公司职员。 案例介绍:求助者上大
有关质子泵抑制药抗溃疡药物(结构通式如图所示),下列说法正确的是 A.苯并咪唑
关于关键线路和关键工作的说法,正确的是()。A.相邻工作的时间间隔为零的线路是
最新回复
(
0
)