首页
登录
职称英语
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
[originaltext] Today I’m going to talk about Germany’s dream airport in Berli
游客
2024-03-11
49
管理
问题
Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、The municipal government kept changing hands.
B、The construction firm breached the contract.
C、Shortage of funding delayed its construction.
D、Problems of different kinds kept popping up.
答案
D
解析
目的原因题。讲座中提到,2012年,检查员发现消防安全系统不合格,之后又发现有90多米的电缆装错了,4,000扇门的序号不对,自动扶梯太短,登记柜台的数量也不够。由此可知,机场不断延期投入使用是因为层出不穷的问题。
转载请注明原文地址:https://www.tihaiku.com/zcyy/3525666.html
相关试题推荐
[originaltext]Whenwethinkofgames,thereareallkindsofthings.Maybeyou’
[originaltext]Whenwethinkofgames,thereareallkindsofthings.Maybeyou’
[originaltext]MyfellowSingaporeans:Whatwereyourmostmemorablemoments
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
随机试题
用于智力测验的是A.心理测评 B.人格测评 C.情绪测评 D.能力测评
运动再学习方法上肢功能训练中,训练腕关节屈伸的是A.仰卧位,让患者用手触摸自己的
关于第四纪地质年代单位的划分,下列哪一组是正确的? A.早更新期、中更新期、晚
DNA和RNA同时存在的微生物是A、原核细胞型微生物 B、真核细胞型微生物
银行间市场可在工作日内的8:30—16:30实时办理转出、转入业务,但交易所市场
下列属于证券公司章程中重要条款的是()。 Ⅰ.证券公司的解散事由 Ⅱ.证券公
小学语文教师在进行教学设计时,常用“会读、会写、会说、会背”等行为动词表述教学目
某投资者以资产S作标的构造牛市看涨价差期权的投资策略(即买入1单位C1,卖出1单
针对审计项目中需要咨询的事项,下列各项中,属于审计项目合伙人应当承担的责任的有(
安全心理学是研究人在劳动过程中伴随生产工具、机械设备、工作环境、作业人员等关系而
最新回复
(
0
)