首页
登录
职称英语
Why does the summit of the Sydney Harbour Bridge increase? [br] [originaltext]W
Why does the summit of the Sydney Harbour Bridge increase? [br] [originaltext]W
游客
2023-10-17
42
管理
问题
Why does the summit of the Sydney Harbour Bridge increase? [br]
W Well, good morning again, everyone, and welcome to "Perspectives" , the weekly New South Wales Radio programme on subjects of general interest from our local area. Today I have in the studio Mr. George Symonds. Good morning, George.
M Good morning, Anne.
W So, what are you going to talk to us about today, George?
M Well, for people from New South Wales and particularly Sydney, this will be of great interest—I hope. I’ m going to tell you a little about Sydney Harbour Bridge.
W Wow! That’ll be so interesting,
M I think so. To start with, I’d like to tell you a little about the size of the bridge. The arch span is 503 metres and the weight of the steel arch is 39,000 tons, (11)The summit is 134m above mean sea level, though it can actually increase by as much as 18cm on hot days as the result of steel expanding in heat. The two pairs of pylons at each end are about 89 metres high and are made of concrete and granite. The steel used for the bridge was largely imported. About 79% came from the United Kingdom but the rest was Australian-made. The granite was quarried in Moroya down the coast, and the concrete is also Australian.
W So, most of the steel used to make our great bridge actually came from England?
M Yes, I’m afraid so. (12)However, the workforce were all Australian!
W Thank God for that. When was the bridge actually built?
M (13)The bridge was opened in 1932 but work first began in 1924, with the construction of the bridge approaches and spans, with two separate teams building the arch on each side working towards each other. The arch was successfully joined on August 19, 1930. I’m afraid that working practices weren’ t very fair in those days and the local government demolished 438 homes which were in the way of the approaches, and as many as 800 families living there were displaced without compensation. The standards of industrial safety were inadequate too. (14)16 workers died during its construction, mainly from falling off the bridge.
W I didn’ t realise that.
M It’ s true. The bridge was formally opened on the 19th March, 1932 by the Premier of New South Wales, Mr. Jack Lang. When it was opened, it was the longest single span steel arch bridge in the world and one of the greatest engineering masterpieces of its time. (15)Several songs were also composed in advance for the occasion but these have now been largely lost or forgotten. However, three postage stamps were issued to commemorate the opening of the bridge and these still exist. One of these stamps, with a face value of five shillings, is now worth several hundred dollars.
选项
A、The United Kingdom.
B、South Wales.
C、Outside of Australia.
D、Australia.
答案
D
解析
根据乔治的介绍,建造大桥的钢材大部分来源于英格兰,但是建造工人全部是澳大利亚人。故选D。
转载请注明原文地址:https://www.tihaiku.com/zcyy/3106267.html
相关试题推荐
WherewasGeorgeWeekesbom?[br][originaltext]Inthissection,youwillhear
WherewasGeorgeWeekesbom?[br][originaltext]Inthissection,youwillhear
Whatdidthemandolastnight?[br][originaltext]W:Sodidyoudomuchyester
Whatdidthemandolastnight?[br][originaltext]W:Sodidyoudomuchyester
Whatdidthemandolastnight?[originaltext]W:Sodidyoudomuchyesterday?M
WherewasAdamborn?[br][originaltext]W:Adam,asyouknow,thisjobisbased
WherewasAdamborn?[br][originaltext]W:Adam,asyouknow,thisjobisbased
Wheredoesthisconversationprobablytakeplace?[br][originaltext]W:Isthat
Wheredoesthisconversationprobablytakeplace?[br][originaltext]W:Isthat
Wheredoesthisconversationprobablytakeplace?[originaltext]W:Isthatsound
随机试题
YouhavemanagedtobungleeverytaskI’vegivenyousofar.______,Iamprepar
Wearetakingthelibertyofaskingyoutosendussomesamplesoftheadvertise
防直击雷装置包括接闪器、引下线和接地体。()
粗集料磨光值试验所使用的新橡胶轮可直接使用。()
2011年,某省全社会研发经费达612.93亿元,RD9(研发)经费占GDP的
下列不属于基金会计报表附注的内容的是()。A.会计期间基金经营成果 B
患者,女性,72岁。入院时体温38℃,心率110次/分,呼吸40次/分,动脉血气
干烤法杀灭芽胞的条件是A.箱温120℃;时间1小时 B.箱温140℃;时间1小
下列做法符合我国法律规定的是:A.某人向法院起诉邻居搭盖房屋,影响自家的采光
某发电厂升压站220kV配电装置的主接线为四角形接线,2台200MW发电机组,2
最新回复
(
0
)