Today I’m going to talk about Germany’s dream airport in Berlin. The airport looks exactly like every other major modern airport in Europe, except for one big problem: more than seven years after it was originally supposed to open, it still stands empty.
Germany is known for its efficiency and refined engineering, but when it comes to its new ghost airport this reputation could not be further from the truth. Plagued by long delays, perpetual mismanagement and ever-soaring costs, the airport has become something of a joke among Germans— and a source of frustration for local politicians, business leaders and residents alike.
Planning for the new airport began in 1989. At the time, it became clear that the newly-reunified Berlin would need a modern airport with far greater capacity than its existing airports. The city broke ground on the new airport in 2006.
The first major sign of problems came in summer 2010, when the construction corporation pushed the opening from October 2011 to June 2012. In 2012, the city planned an opening ceremony. But less than a month beforehand, inspectors found significant problems with the fire safety system and pushed the opening back again to 2013. It wasn’t just the smoke system: many other major problems subsequently emerged. More than 90 metres of cable were incorrectly installed; 4,000 doors were wrongly numbered; escalators were too short. And there was a shortage of check-in desks.
So why, with so many problems discovered, didn’t the airport corporation decide to give up on the project and start over? The reason is simple: people are often hesitant to terminate a project when they’ve already invested time or resources into it, even if it might make logical sense to do so.
The longer the delays continued, the more problems inspectors found. Leadership of the planning corporation has changed hands nearly as many times as the opening date has been pushed back. Initially, rather than appointing a general contractor to run the project, the corporation decided to manage it themselves despite lack of experience with an undertaking of that scale.
To compound the delays, the unused airport is resulting in massive costs. Every month it remains unopened costs between €9m and €10m.
Assuming all goes well, the airport should open in October 2020. But the still-empty airport stands as the biggest embarrassment to Germany’s reputation for efficiency— and a continuing drain on city and state resources.
Questions 22 to 25 are based on the recording you have just heard.
22. What does the speaker say about the dream airport in Berlin?
23. Why was there a need for a new airport in Berlin?
24. Why did Berlin postpone the opening of its dream airport again and again?
25. What happens while the airport remains unused?
选项
A、Tourism industry in Berlin suffers.
B、All kinds of equipment gets rusted.
C、Huge maintenance costs accumulate.
D、Complaints by local residents increase.
答案
C
解析
细节推断题。讲座中提到,更糟糕的是,未启用的机场会产生巨额的费用,每个月的费用高达九百万欧元到一千万欧元。由此推知,这些巨额费用是用在维护上的。
转载请注明原文地址:https://www.tihaiku.com/zcyy/3525667.html
相关试题推荐
[originaltext]Whenwethinkofgames,thereareallkindsofthings.Maybeyou’
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext]AbeetleinvasionintheUnitedStateshaskilledatleasttwenty
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext][12]Intoday’spersonalitystakes,nothingismorehighlyvalued
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
[originaltext]Pianosarenormallyfoundinbuildingforobviousreasons.Howeve
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
[originaltext]W:Hello.M:Hello,isthatthereferencelibrary?W:Yes.CanI
随机试题
可再生能源发电利用率指水电、风电、太阳能、生物质能等非化石能源占一次能源消费总量
渗透性强的砂土变形量完成的较快,而高压缩性土完成较慢。
当发生对基金份额持有人权益或者基金价格产生重大影响的事件时,应在()日内编制并
对机电设备与工器具购置费、联合试运转费之和占工程概算投资额()以上的工程项目,
动员居民关注社区事务,参与社区建设是社区工作的重要内容。在选择动员群众的方法时,
关于证券经纪业务,以下表述正确的有()。 A.在证券经纪业务中,委托人
根据《行政处罚法》的规定,在下列哪种情况下当事人有权拒绝执法人员当场收缴行政处罚
求助者在某一时刻所具有的主观精神世界,其中既包括有意识的心理内容, 也包括那些
下列哪项不是吗啡镇痛药成瘾的精神症状A、情绪低落、消沉、易激惹 B、痴呆 C
管理行为控制程序就是为规范项目施工成本的管理行为而制定的约束和激励机制,内容是(
最新回复
(
0
)