首页
登录
从业资格
Your project is behind schedule due to c
Your project is behind schedule due to c
最全题库
2022-08-02
61
问题
Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider ( ).A、crashing the ScheduleB、performing resource levelingC、conducting reverse resource allocation SchedulingD、utilizing the critical chair resources
选项
A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources
答案
A
解析
由于团队成员之间的冲突,造成项目落后于进度计划,为了解决冲突以使得项目如期完成,你应该考虑:
A.重新安排时间表
B.实行资源调配
C.执行逆向资源分配调度
D.利用关键的主要资源
转载请注明原文地址:https://www.tihaiku.com/congyezige/2297222.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
Inaprojectplan,whentheprojectmana
( )isaprojectmanagementtechniquefo
Inprojectmanagement,a( )isalist
Toensuretheprojectteamprovidesthe
Ascheduleiscommonlyusedinprojectp
TheProjectManagementTriangleisamod
Inprojectmanagement,a( )isalisto
Theprojectbudgethasbeenfinalized.Ad
如果在一个课程注册系统中,定义了类CourseSchedule和类Course,
WhichofthefollowingProjectScopeMan
随机试题
Wasitenvisionedfortheeurotoeventuallybecomesuchastrongcurrencyt
Whydidshetakeupjournalism?[br][originaltext]M:TinaWhite,somepeopled
[originaltext]TheUnitedStateshasthelargestmyintheworld.Thesizeofan
[audioFiles]audio_etoefz_025(20051)[/audioFiles]A、Helpthewomanrepairhercar
ComparedwiththefirstannulpollconductedbytheNationalSleepFoundation,2
图示结构用位移法计算时,其基本未知量的数目为: A.3 B.4 C.
(2018年真题)下列选项中,不具有法人资格的是()。A.股份有限公司 B.
下列哪项不是紫苏的主治证A.阳虚水肿 B.风寒表证 C.妊娠呕吐 D.鱼蟹
下列关于宫颈脱落细胞学叙述不正确的是A.萎缩性细胞改变也可出现在中青年 B.宫
甲乙两个互斥方案寿命期相同,甲方案的内部收益率为15%,乙方案内部收益率为12%
最新回复
(
0
)