问题
Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
选项
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
答案
A
解析
前导图法是用于活动排序的技术。前导图法包括四种活动依赖关系。先行活动结束后续活动才能开展的关系是结束—开始关系。
转载请注明原文地址:https://www.tihaiku.com/congyezige/2295978.html
本试题收录于:
高级信息系统项目管理师题库软件水平考试初中高级分类
高级信息系统项目管理师
软件水平考试初中高级
相关试题推荐
( )isamethodusedinCriticalPathMe
Whichofthefollowingschedulingmethod
()isamethodusedinCriticalPathMeth
()isamethodusedinCriticalPathMeth
()amethodofobtainingearlyfeedbacko
PrecedenceDiagrammingMethod(PDM)isa
PrecedenceDiagrammingMethod(PDM)isa
()amethodofobtainingearlyfeedback
Projectselectionmethodsinvolvemeasur
PDMisamethodofconstructingaprojec
随机试题
Writeanoteofabout50~60wordsbasedonthefollowingsituation:Lastw
Insuchachanging,complexsocietyformerlysimplesolutionstoinformation
喜悦之情joyousfeeling
___________(科学家们将会提出)newmethodsofincreasingtheworld’sfoodsupply.Scient
2012年,全国国内旅游人数29.57亿人次,比上年增长12.0%。其中,城镇居
王老师的日历如下图所示。他每天清晨撕下前一天的那页日历,某天下午,王老师将最近撕
(2019年真题)为落实“健康中国”战略部署,某社会工作服务机构整合资源,提供多
A.国家卫生和计划生育委员会 B.人力资源和社会保障部 C.国家发展和改革委
危险废物填埋场场址必须有足够大的可使用面积以保证填埋场建成后具有()年或更长的使
竣工决算财务报表之间的逻辑关系是()。A.勾稽关系 B.平衡关系 C.相符
最新回复
(
0
)